
Resources
Protection Through Lien Rights
WHAT IS A MECHANIC’S LIEN?
A mechanic’s lien is a statutory right in Georgia to proceed against the real property. It is an extremely effective option to ensure payment for goods and/or services rendered. In Georgia, it is the only way to recover against those parties with whom you have no contract. Basically it is a foreclosure process behind existing security interests. Because liens are in derogation of common law rights, they are strictly construed against the claimant. Thus, a party seeking to enforce a lien must be extremely careful to ensure that all the necessary procedures are followed.
All 50 states provide lien rights but the rights and procedures vary widely. This article only discusses the process and procedures for Georgia liens. Do not assume that the procedures in any other states are even remotely similar to Georgia. In the event that you intend to do work outside of Georgia, please contact us or an attorney that practices in the work local to ensure that you file the proper notices to protect any lien rights.
It is important to note that lien rights are in addition to contractual rights. Thus, Owners and General Contractors who have not properly protected their interests can be forced to pay twice for the same goods and services.
WHO IS ENTITLED TO MECHANIC’S LIEN PROTECTION?
HOW ARE LIENS DECLARED, CREATED AND PROSECUTED?
In order to declare, create and prosecute a lien you must have done the following:
** The total amount of liens cannot exceed contract price – generally not an issue.
HOW DO YOU DISSOLVE A LIEN? (NOT THE SAME AS BONDING OFF A LIEN)
A lien can be dissolved through the following:
LIENS OF THOSE WITHOUT DIRECT CONTRACTUAL RIGHTS
If a party seeks to file a lien against property in which it does have a direct contractual relationship with the Owner or the General Contractor, there can potentially be additional notices required. Whether an additional notice is required depends on whether a Proper Notice of Commencement has been filed.
1. Notice of Commencement
In order to ensure notice of parties providing labor or materials for parties not in a direct contractual relationship, an Owner or General Contractor should file a Notice of Commencement. A Notice of Commencement requires suppliers and sub-subcontractors to provide notice of being on the project or forever be barred from asserting any lien rights on the Project.
A “Proper” notice of commencement has been filed by the General Contractor. A “Proper” Notice of Commencement must follow the procedures listed below:
A. The Notice of Commencement must be filed “not later than fifteen days” after physical commencement on the Project;
B. The Notice of Commencement must be filed with the clerk of the superior court of the county where the property is located;
C. The Notice of Commencement must posted at the site. (We strongly recommend that a photograph be taken of the Notice of Commencement after is has been posted).
D. The Statute requires that a Notice of Commencement contain the following:
i. name, address and telephone number of contractor;
ii. name, and location of project and legal description;
iii. name address of true owner (correct legal name);
iv. name and address of person other than the owner at whose instance improvements being made. (i.e. leases).
v. name and address of surety;
vi. name and address of construction lender
*** Lien laws are strictly construed against the claimant, and thus substantial compliance with the above may be sufficient. However, to ensure that the Notice of Commencement is valid we recommend and advise that all of the above requirements be provided.
E. If a subcontractor provides a written request for a Notice of Commencement, the Contractor must provide a copy within ten days of a written request2. Notice to Contractor
A “Notice to Contractor” is necessary if and only if a valid notice of commencement has been filed. If a Notice to Contractor is required, it must be provided to the Owner or Contractor within thirty (30) days after the filing of a Notice of Commencement or within thirty (30) days of the first provision of labor or materials to the project.The Notice to Contractor must contain the following:
A. name, address and telephone of person supplying labor or materials;
B. name and address of person to whom labor or materials are being supplied (sub e.g.);
C. name and location of project;
D. description of services, labor being provided; and
E. the contract price or the anticipated value of the labor and/or materials
HOW DO YOU RELEASE A LIEN?
LIEN WAIVERS
CONCLUSION
The Georgia Lien statutes contain many pitfalls and potholes that can impede your ability to collect for labor and services provided. Thus, the most pressing advice that Stone & Bellus, P.C. can provide is to be careful and follow the procedures exactly as provided by statute.